APR services returned today to fill in gaps in the laser scan survey. Parts of the stove house areas of Stove House 1 and Stove House 2 were inaccessible when the main scan was carried out earlier in the work programme.
Decayed floor beams, and the collapsed roof structures which had fallen on top of it have now been removed and props inserted below the floor beams. This is one of the older areas of the Lion Salt Works dating to about 1894.

Walkways (left) have been inserted from the Loading Bay / Packing Area to provide safe access for the architects and engineers to prepare the Phase 2 schedule of works and cost plan, prior to going out to tender for the main restoration work.
Moving south from the Packing Area you move into Warehouse 4 which has a huge crushing mill (right) used to convert dried blocks of salt back to loose crystal salt and pack them into sacks.

Moving south from the Packing Area you move into Warehouse 4 which has a huge crushing mill (right) used to convert dried blocks of salt back to loose crystal salt and pack them into sacks.