Lionel Visits End of Enabling Works

Lionel was on holiday last week so has only just been able to upload his visit to the Lion Salt Works to meet the William Anelay's team on 5th November before they left site.
He was able to pose for pictures and walk around the site and see how it has changed over the previous 15 weeks.
Some before and after views will be posted in the next few days.
Cheshire West and Chester Council will hold meeting at the end of November to establish how the project to restore the whole site will be taken forward.

Wednesday, 5 August 2009

WEEK 2 - Day 7 Meet the Enabling Team


Our Enabling Team are from the renovation and restoration company William Anelay's, specialists in the repair and restoration of historic structures.


Front row from left to right : Ken Jones, Chris Watson, Adam McKechnie, Simon Allen


Back row from left to right : Chris Winnington, John Watts and David Marsh.

Dave Marsh is the Anelay's Small Works and Contracts Manager and Site Manager for the Lion Salt works project. Chris Watson and Simon Allen both work with Anelay's, whilst Ken, Adam, the other Chris and John have been recruited locally from the Northwich area.
For a web link to William Anelay's go to the Contractors panel on the left and click to visit their web site and see the projects the company has worked on in the past.

Wednesday, 29 July 2009

WEEK 1 Day 1-2 - Setting up the Site

After all the fundraising, planning, site reports and studies - work is actually begining on site. You know it really has all started when the contractor arrives to set up on site, the full safety information gets posted, and you need those hard hats, high viz jackets and steel toecap boots.

The business end of the project has now been handed over to the contractors to begin the programme of 'Enabling Works' which is the First Phase of Restoring the Lion Salt Works.

The work will be described briefly over the coming weeks and we will follow the progress as it is carried out and completed. The Lion Salt Works Team at Cheshire West and Chester Council will be introduced together with the Design Team and Contractors.

The site is being divided into two sections - the northern sector, where the main salt works complex lies; Pan Houses, Brine Tank and the Pump House. This area is to be secured as the working area.

The southern half of the site will remain open for visitors during fixed opening times, but will be secured by a perimeter fence, again to make the site totally secure. The Lion Salt Works Trust and Friends of the Lion Salt Works will continue to open the exhibition centre in the former Red Lion Inn and pass on information about the history of the site and the progress of the restoration works as things move forward.







The first fence panels being erected around the northern perimeter of the site fronting the Trent and Mersey Canal.









Dividing the site in two. On a wet and dismal day at the end of July.