Work is carried ouut safely from the scaffoldng erected inside and out side, and from roof ladders.
The roof cladding had a felt membrane underneath it, which has protected the underlying boarding from the weather. The boards will be removed carefully and stored for reuse when the Stove House is rebuilt, but a non-asbestos substitute cladding will provide the final roof finish.
The asbestos sheets are removed by carefully cutting the fixing bolts and lifting the sheets of whole. The sheets are stacked on the scaffoold before being lowered to the ground for wrapping and transport off site.
The asbestos sheets are removed by carefully cutting the fixing bolts and lifting the sheets of whole. The sheets are stacked on the scaffoold before being lowered to the ground for wrapping and transport off site.