Showing posts with label SH5. Show all posts
Showing posts with label SH5. Show all posts

Thursday, 29 October 2009

WEEK 14 - Day 55 Dismantling West Gable & Final Work to Stove House 5


The unsafe sections of the west gable of Stove house 1 were dismantled today. The area will be protected by sheeting over the winter.
The curved section of wall may incorporate the original garden wall of the entrance to the Red Lion Hotel, after which the salt works was named can be seen more clearly now. At this height the wall curves and has a sleight batter as it rises from the road level. it is also one and a half bricks wide.
The final remnants of Stove House 5 were removed from site this afternoon, all the parts not being saved for reuse that is.
There will be some before-and-after photographs posted next week to show how the site has changed over the last fourteen weeks.

Thursday, 22 October 2009

WEEK 13 - Day 51 Clearing Salt, Stove House 5 and Laying Paths

Salt can set like concrete once it gets into the fabric of a building and is baked hot and stays dry.
Within stove Hose 1 we had to chip out the remaining salt with a percussion hammer.
The flue walls in this area have been robbed out many years ago but the remains of the walls indicate the layout of the flues and ditches which ducted the hot fumes from the Pan House to the chimney built on Ollershaw Lane.



Meanwhile the big digger spent a fourth day removing the ash, cinders and flue walls from the dismantled Stove House 5.
Over 100 tons of material has been removed from site. The materials which made up the infill of the stove house were themselves waste products of the Lion Salt Works. Henry Thompson used waste cinders deposited at the south side of the site that were raked from the earlier pan houses over decades of salt making.

Alongside all the dismantling and removal of contaminants we are also being constructive and looking to the future. Sue Beesley and Isabel Brookes have begun the creative landscaping that will transform the south west corner of our salt works into a tranquil butterfly garden in partnership with George Martin and the Butterfly Conservation gardening volunteers.



Wednesday, 21 October 2009

WEEK 13 - Day 50 Dismantling Stove 5

Work continued to dismantle Stove 5. In total 600 tons of ash, cinders and bricks have been removed since Monday. The position of the outer North wall is shown by the far left ranging rod.

Tuesday, 20 October 2009

WEEK 13 - Day 49 Cleaning Pan 5 and Starting Butterfly Garden

The clearance of the ash and cinders from Stove House 5 continued. There should be 18 lorry loads removed over the day, each carrying an average of 17 tons a trip. Salt also continued to be removed from Stove 1.



Two new activities started today. Cleaning of the salt pan moved from Pan House 5 started with a manual knocking of of surface debris. Apologies are due to all our neighbours for the resulting banging and hammering. this must have been what it was like when the salt pans were in use. The traditional practice was to 'pick' a salt pan pm a Monday morning to remove build up of pan scale and salt from the previous weeks salt making, so that fresh brine start to be heated for the new week.
The underside of the pan shows many original rivetted plates which have had new plates welded over the top. It has a patchwork appearance of overlying metal plates.
In the south west corner a cotter pin and patch was still in place. Phil was able to gentle tap the wedge out and take the drain patch apart.










We also began laying the paths for a recreational area to the south west of the site, which will be planted as a buddlea garden. This is funded by a landfill grant contribution made by Ineos Chlor via the Mersey Forest team. The paths are being edged today and will have hardcore laid over a membrane tomorrow.

Monday, 19 October 2009

WEEK 13 - Day 48 Stove House 1 and Stove House 5

Activities today involve dismantling three areas - the gable of Warehouse 1, salt from within Stove 1 and the stove area of Stove House 5.

To carry out the work safely external cladding has been erected along the side of the building.

Portable conveyor belting was installed to easy the manual handling of the salt debris from the stove area.

You can now really see that the stove area ran off from the Pan House at the first floor level. The machine tearing up the ash and cinders is really working hard because salt and brine has soaked into the fabric of the brickwork and the cinder base, setting like concrete in the high heat of the salt making process.


Thursday, 8 October 2009

WEEK 11 - Day 43 Salt Pan 5, Laserscan and Pan House-Warehouse 4

The team is rapidly dismantling the Stove House 5 and preparing to lift the salt pan off the furnace so that it can be shot blasted and given a protective paint. H&E Scaffolding are now taking down scaffolding and removing it from site, so we can really see that the contract is getting close to completion.



A magnetic drill was used to drill the holes in the lifting beams below Pan 5. This type of drill clamps itself to the iron beam by an induction magnet so that the steel can be drilled. Galvanised bolts were then tightened to clamp the two girders together. Wooden packing pieces will be inserted between the girders and the underside of the pan in preparation for lifting the pan off the furnace base on Tuesday, next week.

APR services returned today to fill in gaps in the laser scan survey. Parts of the stove house areas of Stove House 1 and Stove House 2 were inaccessible when the main scan was carried out earlier in the work programme.
Decayed floor beams, and the collapsed roof structures which had fallen on top of it have now been removed and props inserted below the floor beams. This is one of the older areas of the Lion Salt Works dating to about 1894.
Walkways (left) have been inserted from the Loading Bay / Packing Area to provide safe access for the architects and engineers to prepare the Phase 2 schedule of works and cost plan, prior to going out to tender for the main restoration work.
Moving south from the Packing Area you move into Warehouse 4 which has a huge crushing mill (right) used to convert dried blocks of salt back to loose crystal salt and pack them into sacks.

Moving past the crushing mill to the south end of Warehouse 4 (left) you can see that this warehouse is unusual in having an iron frame. The floor has the same hatches used to 'loft' salt from Stove 4 on the floor below. From the end of this warehouse you can look down into Pan 4 (right). Pan House 4 was built by Alan Thompson.

Monday, 5 October 2009

WEEK 11 - Day 40 Preparing Pan 5 and Recording Stove 5 Flues

The two long 'I' beams were installed today along the north and south sides of the salt pan No.5. Each beam weighs one ton. Five lighter 'I' beams will be inserted underneath the pan and will be clamped to each of these lifting beams. The pan base is buckled through use and will have packing pieces inserted between the steels and the under surface so that the weight is carried evenly. Only when we are sure the pan can be carried safely will it be lifted. This might be later this week, or early next week, so keep logging on to see developments.


With the east gable dismantled and the brick wall removed from below it we can see how the stove area is constructed. Hot gases from below the salt pan are drawn along flues within the Stove House to dry the salt. The lower part of the flue is set within ash and cinders, lined with brick but due to the heat and fumes the bricks are very badly corroded and decayed. Many bricks have turned to powder, some are heavily impregnated with white salt crystals. The flues are carried above the ash and cinders with brick upstands to create 'ditches' between the flues. There has been a build up of salt within the ditches which is over 20 centimeters thick.
A bag wall slows the passage of gases as they pass from the the pan house into the flue system. There is a thick layer of fly ash throughout the whole structure.
Metal plates sit over the flues so that salt blocks can be placed directly over them. These metal plates have corroded heavily after twenty years in a now cold, damp unheated building covered in salt.
The inner surface of the flues have suffered the most and with e mortar having broken down many walls have simply collapsed into the ditches and flues.

Most of the dismantled timbers have now been assigned racking space within the timber store and are being graded for condition and re-use when the structure is rebuilt. Some pencil marks were seen when the trusses were dismantled, but today we found some carpenters marks cut into a beam which had been re-used as a supporting joist within the Loading Bay. There are carpenters marks in other re-used timbers in Stove House 3.

Thursday, 1 October 2009

WEEK 10 - Day 39 Dismantling Brickwork

The east gable brick work is being taken down today. This supported the east gable timber framing which was removed earlier in the programme. This wall is three bricks thick, unlike the other three walls which are only two bricks thick. Also the mortar comprises a hard concrete mix, so it is taking longer to remove.
Another sunny day, after a cloudy start. Excellent for getting on with the work in hand.

The removal of the wall provides easier and safer access to work around the salt pan and to have easier access inside the remains of the stove house. The interior is really poor condition, mostly the depredation has been caused by vandalism by intruders over the years in which the site was abandoned.
Four scaffold towers are being constructed at the east end of the salt pan. These will hold the pan temporarily whilst it is shot blasted and painted.
During next week steel girders, delivered yesterday will be inserted under the pan and the whole structure will be lifted and turned through 90 degrees.
The remains of the furnace will be dismantled and recorded before the pan can be returned to its original location, but replaced at ground level.

Wednesday, 30 September 2009

WEEK 10 - Day 38 Removing Floorboards and Steel Delivery

The whole of the warehouse floor of Stove House 5 was removed today, allowing us to prepare to take away the floor joists and the the side walls.

The dismantling of the walls will begin with the east gable so that the scaffold team from H&E Scaffolding, Telford can insert lifting girders beneath the salt pan.

The floorboards rest on a timber beam laid over the joists, which are in fact second hand railway lines.

The floor boards have been affected by the process of drying the salt. The upper surface is very smooth, but the lower surface has had fibres drawn from the cell walls of the wood by the damp heat trapped between the floors as the salt dried over the flues.


The steel beams weigh almost 4 tons and were delivered from the Corus steel works at Scunthorpe.

They have been laid out alongside the salt pan ready to be inserted underneath for lifting the pan.
Following the lift next week the iron pan will be cleaned and prepared for a protective coat of paint.
Asbestos roof sheets were removed from above Warehouse and Stove areas 1 and 3. Stove 1 is the oldest part of the Lion Salt Works and has some difficult structural areas because it has been adapted and altered gretaly over its life. A scaffold walkway is being inserted and additional props to support the floor and roof areas.
Video for work completed on Day 21 to dismantle roof trusses has now been posted at http://www.youtube.com/watch?v=4nizNmZ6RWA

Tuesday, 29 September 2009

WEEK 10 - Day 37 Dismantling Floorboards of Stove House 5

Work started today to dismantle the floorboards of Stove House 5. The boards are being lifted for replacement whn the building is rebuilt on new foundations in Phase 2. Following the removal of the boards the floor joists will be taken out and the outer walls will then be taken down brick by brick. There are over 400 boards to lift before lunchtime tomorrow.

Also posted today a movie prepared by APR Services to show the coverage obtained during their laserscan survey of the Stove House areas of SH 2,3, 4 and 5. http://www.youtube.com/watch?v=bmRBwrhPs30m/watch?v=bmRBwrhPs30
The NW Industrial Archaeology Panel held their meeting at the Lion Salt Works today. Left to right: Ian Miller, Oxford Archaeology North; Julian Baum, Take 27; Mike Nevell, Salford University; PaulineWeb, Museum of Science & Industry Manchester; David George

Monday, 28 September 2009

WEEK 10 - Day 36 Walls of SH5 Removed to Warehouse Floor Level



With the roof trusses removed work on Stove House 5 continues to dismantle and remove the brick works. First this is being taken down to the warehouse floor level so that the floor boards can be removed.

A timelapse sequence was posted today of the removal of the asbestos roof sheets and timber boarding of Stove House 5.
Visit it at http://www.youtube.com/watch?v=UIMyJrvP4EM . A sequence showing the dismantling of the roof trusses will follow.

Thursday, 24 September 2009

WEEK 9 - Day 35 Removing Scaffolding, Racking and Other Works

Having removed the last roof trusses all the scaffolding erected inside the roof space can now be taken down. On Monday all the scaffold tubes above the warehouse floor will have been removed. The tubes and boards will now be used to build walkways and props within the main core of the salt works.
Looking from the north east the main salt works buildings can be seen through the scaffold tubes. The hatches allowing salt blocks to be 'lofted from the stove (hothouse or 'otters'- see below)' to the warehouse floor are covered with plyboard to avoid anyone falling though. The floorboards of the warehouse floor will be removed next week when we can show you the detailed construction of the flues within the stove area.

The scaffold racking is now being built to store the truss elements, roof boards and other structural pieces. As each timber is put into storage a condition report is made grading it with a recommendation as to whether it is OK to be re-used, if it needs a repair or if it should be used as a pattern for a new piece to be made.

Within the main complex 110volt festoon lighting allows the other stove ('otters') areas to be cleared of debris and supports to be inserted to the warehouse floor above. Compare these areas with the dismantled section of Stove House 5 over the coming weeks.
The Enabling Works will allow safe access to the architects to inspect these parts of the salt works so that we can prepare a schedule of works and go out to tender for repairs to costed in Phase 2. The Stove House has flues and ditches where the salt blocks were dried.
Within these areas the decades of salt build up in the ditches and ash in the flues will be cleaned out. The condition of the cast iron columns, which have deteriorated in the salt are of particular interest to the overall stability of the buildings.
A video has been placed on the Cheshire Museums YouTube channel where the timelapse camera installation can be seen. click on http://www.youtube.com/watch?v=Nt9TkGwrohY . This is continuing to record work to dismantle Stove House 5 and will form a special video compressing the work ove the past weeks to a few minutes.

Wednesday, 23 September 2009

WEEK 9 - Day 34 Last Roof Truss of SH5 Dismantled


The last pieces of roof trusses were removed from Stove House 5 by lunch time today.
After a damp period yesterday our luck held and today was again dry and warm.
The large forklift took more pallets of timbers to the ground ready to be stored in our temporary building.

H&E scaffold team were hard at work along side Anelays removing unwanted sections of scaffold. The internal platforms are being removed and the upper sections of brickwork are to be taken down to the warehouse floor level. after which the floor boards themselves will be taken to the timber store.



A1 Environment Services came out into the daylight after long periods inside Warehouse 2 and 3 removing collapsed pieces of cement asbestos roofing sheets which have fallen onto the internal floors.

Tuesday, 22 September 2009

WEEK 9 - Day 33 Roof Trusses almost Down - Internal Works

Having had a couple of weeks of dry weather it was back to rain from lunch time, a soft drizzle with grey low cloud. Uncomfortable for those completing the dismantling of the roof, and dark for those within the pan houses and stove houses. But it dried up and stayed warm for the afternoon, so work continued quickly. Our working scaffold has itself started to be dismantled, working back from the east gable. The traget is to have all the roof timbers dismantled by end of work tomorrow, Wednesday.

Monday, 21 September 2009

WEEK 9 - Day 32 Continuing Works and Visit

A1 Environment continued removing asbestos roof sheets from the former Salt Pan 2.
H&E Scaffolding continued erecting a scaffolding walkway through and around Salt Pans 3 and 4. William Anelay Ltd continued to dismantle the roof trusses of Stove House 5, and with the weight removed from the east gable the upstanding brickwork above the warehouse floor was also dismantled.
A video recording the dismantling of the east gable has been posted on Youtube and a link placed in last weeks diary account. Editing of the video taken as roof truss No.6 was dismantled is also now uploaded http://www.youtube.com/watch?v=4nizNmZ6RWA.
Carolyn Shepherd took away some more timbers which are not required in the rebuilding phase and these will be used in an art installation as part of her 3rd Year art degree exhibition.
Middlewich Town Clerk, Jonathan Williams and Kerry Fletcher, Heritage Development Officer visited to see the progress of the Enabling Works. The brine pump of Murgatroyds Salt Works still survives in Middlewich and was operated by Tom Lightfoot whose manuscript and pencil drawings were edited and published by Annelise Fielding as 'Open Pan Salt Making in Cheshire' (see publications link opposite).




Dismantling roof trusses (left view from north) (right view from south)


Details of ridge boards showing diferences in construction between the ridge above the main trusses (left) and the ridge over the roof ventitator.