Monday 19 October 2009

WEEK 13 - Day 48 Stove House 1 and Stove House 5

Activities today involve dismantling three areas - the gable of Warehouse 1, salt from within Stove 1 and the stove area of Stove House 5.

To carry out the work safely external cladding has been erected along the side of the building.

Portable conveyor belting was installed to easy the manual handling of the salt debris from the stove area.

You can now really see that the stove area ran off from the Pan House at the first floor level. The machine tearing up the ash and cinders is really working hard because salt and brine has soaked into the fabric of the brickwork and the cinder base, setting like concrete in the high heat of the salt making process.