Wednesday 12 August 2009

WEEK 3 - Day 11 Scaffolding arrives

Scaffolding arrived this morning to begin supporting the outside of Stove House 5 and to provide a working platform from which to survey and dismantle the link walkway between Stove House 5 the main complex of Stove House 1 and 2. The first wagon of poles was waiting outside the site on Ollershaw Lane at 7am, ready for off loading. You can see the Salt Store on the opposite side of the road to the Lion Salt Works.







On site the first set of poles and planks are off loaded and moved to the Loading Bay area.







The first area to be scaffolded is this area at the north end of the Loading Bay to allow safe access to the overhead walkway which provides access from the warehouse floor of Stove House 5 to the main complex of earlier pan houses. This link walkway will be first building element to be dismantled, prior to the later dismantling of the whole of Stove House 5.
An asbestos survey is being undertaken to identify remaining asbestos on site and to prepare a method statement for safe removal.

Also being labelled is the collapsed headstock from over the first brine shaft of 1894.