Thursday 6 August 2009

WEEK 2 - Day 8 Review of Days 1-8

The vegetation has been cut back and cleared to allow access to all parts of the compound area. Stored objectes have been 're-found' and we can now see the brine pump etc.
The area around Stove House 5 is being cleared to allow it to be scaffolded prior to dismantling.
More on this next week.
A video diary of some of the preparation works is linked below.

http://www.youtube.com/watch?v=lMUV8qz5uyQ

The view from the first floor woindow of teh former Red Lion Inn, looking north east. We hope to film a time lapse sequence of the work being carried out to dismantle and rebuild Stove House 5 from this view point.

1 comment:

  1. It's fantastic that you are able to provide so much online information - blogs, photos and video diary - Andrew, you're a real hi-tech archaeologist and a real gem for this project. Keep up the good work! Artist Carolyn

    ReplyDelete

Please leave your cmments about the work to restore the Lion Salt Works.